Acton Diveunder


West London

Bauer Technologies was awarded this £4m contract by principal contractor, BAM Nuttall, which required Bauer Technologies to install secant and contiguous pile walls.

 

The works were executed within the live rail environment, within a shunting yard adjacent to the Acton Main Line.  Each working day was meticulously planned around train movements, access restrictions and pile installation cycles. Working closely with a specialist team of engineers from BAM Nuttall, Bauer Technologies developed a robust process for ensuring advanced Adjacent Line Open (ALO) drawings were approved by BAM Nuttall, to allow the works to continue without causing delays.

 

Phase 1 of Bauer’s scope of works commenced in April 2013 and was completed in August 2013.

Phase 2 of the project commenced in March 2014 and was completed in May 2014.