Tottenham Court Road Station Upgrade


London

In December 2009, BAUERKeller JV was awarded the contract to perform the foundation works at the Tottenham Court Road Station Upgrade project for London Underground. The contract was awarded by BAM Nuttall/Kier JV, on behalf of main client Crossrail.

 

The Joint Venture between Bauer Technologies and Keller allowed both parties to concentrate on their strengths with Bauer Technologies’ scope involved rotary piling and diaphragm wall works. The plunged columns installed by Bauer Technologies on site were by far the heaviest and longest the industry had seen for quite some time.

 

The site works operated late into the night with night-time work having to be carried out quietly (due to noise regulations), noise restrictions also applied by day.